Tiszafüred free beach
The aim of the Tiszafüred mayor's office was to create a water surface that could be used in a relaxed way, without the problems coused by the aquatic plant - perhaps familiar to everyone - called the sulyom (water caltrop). Unbelievable dimensions, large product quantities, the right shaping of the floating pier, keeping in mind to maintaining the rigidity of the frame. A GRANDIOSE DESIGN!
In the first months, we planned, countless ideas were drawn up for the formal design, which were followed by many, many hours of consultation, before the plan for the framework of the beach was born.
Production has begun, followed by construction in spring. We arrived on the day set for the start of construction full of curiosity and anticipation.
The products arrived, we got out the drawings and everyone was ready to deliver the biggest project in our company's history.
The weather caught up with us many times during the one-week period of the project, and on a daily basis we were regularly invited to take a break by a heavy shower/thunderstorm. But the lake Tisza always compensated when the sun came out again and a rainbow appeared in the distance.
We placed countless module elements one behind the other and screwed on the necessary accessories - cordon pole supports, bathing ladder, mooring cleat - to finally achieve the shape shown on the plans. It was a beautiful sight and an uplifting feeling that we brought it all together.